Traffic Advisories

The following traffic advisories reflect current conditions as they are known. The listings below reflect construction work that can affect travel on city streets, sidewalks, and trails. Expect traffic delays or use an alternate route, if possible. Please obey construction signs and flaggers. Construction will be conducted in accordance with COVID-19 safety precautions.

This page is regularly updated. To receive updates via text or email, please subscribe to our LebAlert system. To verify the current status or give feedback, please use the contact information listed with each advisory.

Last updated: 06/22/2021 1430 hours.


Active Projects


CSO #13 Project

  • Status: This project is the last of the Combined Sewer overflow projects that the City is undertaking to meet the EPA consent decree. The project's main goal is to take the stormwater out of the sewer mains so that overflows do not occur at the permitted outfalls along the Mascoma and Connecticut Rivers. While this work is being done the City is replacing the old infrastructure at the same time as a holistic approach.

    This project entails approximately 1400 linear feet of roadway construction along South Main Street (12A), with the replacement of storm lines, sewer lines, waterlines, roadway, and new sidewalk and bicycle lanes and 800 linear feet of work in the Romano Circle area encompassing the same type of infrastructure work. Notts Excavating was the low bidder. The project began on June 14th and will continue to the beginning of Nov 2021 with a winter shutdown and then will resume in the spring of 2022 with final lawn restoration, final pavement, and striping.

    Traffic will be kept open along 12A but will be reduced to one lane, alternating traffic. People traveling along this route should expect long delays. 
  • Managed By: City
  • Contact: Christina Hall
  • Project Page: LebanonNH.gov/CSO13

Hillcrest Acres 

  • Status: Final paving on Prospect Street and paving on Moulton Ave. is planned for July 2021. Hillcrest Drive, Skylark, Ledgelane final paving is scheduled for Spring 2022. 
  • Managed By: City
  • Contact: Christina Hall
  • Project Page: LebanonNH.gov/Hillcrest

Mechanic Street Paving (CSO#11, CSO#12)

  • Status:  Final paving and line striping of Mechanic Street is complete. Final paving and line striping for Mascoma and Bomhower Streets, as well as Freeman, Ora, Myra, and Avon Avenues will occur mid-July 2021.
  • Managed By: City
  • Contact: Christina Hall
  • Project Page: LebanonNH.gov/CSO11, LebanonNH.gov/CSO12

Miracle Mile Pedestrian Improvement Project

  • Status: Pine hill Construction will begin work on June 28, 2021, and work will be completed prior to October 1, 2021.  The westbound bicycle lane will be closed during construction. At times, the westbound travel lane will be closed to vehicle traffic and will be coned off and traffic diverted to the center lane for westbound travel.
  • Managed By: City
  • Contact: Christina Hall
  • Project Page: LebanonNH.gov/MiracleMile

Route 12A Dry Bridge Replacement Project